Waterproofing a Bathroom Floor Step by Step: Primer, Membrane and the Waiting Between Coats
A DIY bathroom floor waterproofing method, from primer and silicone to membrane and two coats, adapted for Indian bathrooms.
7 October 2026 via Bunnings Warehouse
Most bathroom leaks that reach the flat below don’t start in the middle of the floor. They start at corners, along the joint where the wall meets the floor, around the drain and through hairline cracks nobody bothered to treat. The video we’re looking at today is a short Australian DIY demonstration. Under the hardware-store branding, it follows the same logic any decent waterproofing job should: prepare the surface, prime it, treat the weak points, reinforce the joints, apply two coats and give every layer time to cure.
Let’s walk through it, then talk about what changes when the bathroom is in a Chhatrapati Sambhajinagar flat rather than a Sydney suburb.
The tool and material list
The presenter lays everything out before starting, and that habit alone avoids half the mistakes on site. Here’s the kit:
- Cleaning equipment (broom, vacuum, damp cloth)
- Safety gear, including gloves, because liquid membrane is messy
- Primer and a stirrer
- Hammer, utility knife and scraper or spatula
- Spirit level
- Reinforcing membrane (a fabric roll)
- Caulking gun with silicone
- The liquid waterproofing product itself
- Masking tape, a roller and a paintbrush
Nothing exotic. The difference between a floor that stays dry for 15 years and one that leaks in 15 months is rarely the material. It’s the sequence and the patience.
Step 1: Clean until it’s genuinely clean
“With our first step, we’ll be cleaning the area free of dust and make it nice and smooth.”
Dust is the enemy of adhesion. A membrane painted over loose dust sticks to the dust, not to the slab. In Indian sites you’ll also find old tile adhesive, cement lumps, POP splashes and oil. All of it has to come off. Chip off any high spots and make sure the surface is sound. Hollow-sounding plaster gets broken out and redone.
Step 2: Prime from the back corner forward
“When applying your primer, it’s good to start from the back corner and work your way forward. It’s also good to go up the wall a little bit.”
Two lessons here. First, never paint yourself into a corner. Start furthest from the door and work out. Second, take the primer up the wall. The floor-wall junction is the single most important line in any bathroom, and the waterproofing must turn up the wall continuously, not stop at the floor edge.
The presenter also says to follow the manufacturer’s instructions for the primer. That sounds obvious, but dilution ratios matter a lot. A primer that’s too thin won’t seal the pores, and one that’s too thick sits on top as a skin.
Step 3: Fill the cracks, then wait
Once the primer is dry, cracks get filled with silicone and the excess is scraped flush with a spatula. Then comes the part most people skip:
“I’ve now waited 24 hours for the silicone to dry.”
Twenty-four hours, before a single coat of waterproofing goes on. On Indian sites, cracks in the slab or screed are more often treated with a polymer-modified repair mortar or a flexible crack filler than with silicone, but the principle is the same. Treat every crack and every junction before the main coating, and let the filler cure.
Step 4: Mask the boundary and decide the height
“I’m doing the bathroom floor, but if I was going up to the shower recesses, I would have to go, at least, 1.8 meters high.”
Masking tape marks exactly where the waterproofing will stop, so you get a clean edge. The 1.8 m figure for shower areas is worth remembering. Indian bathrooms rarely have a separate shower enclosure. The whole room is often the wet area, with a wall shower spraying across two walls. In that layout we’d treat the shower walls up to at least shower-head height, and the rest of the room’s walls to a comfortable skirting height above the floor.
Step 5: First coat, with membrane bedded into the joints
This is the heart of the method. The first coat of liquid waterproofing goes on, again from the back corner forward. While it’s still wet, strips of reinforcing membrane are laid over the joints and cracks:
“I’m just doing bits at a time so I can still reach to the corners.”
“Now in order for this to stick, I’m going to apply some more waterproofing on top of it.”
So the sequence at every joint is wet coat, then fabric, then more coat on top, with the fabric sandwiched in the middle. The fabric acts like the steel in RCC. It gives the coating tensile strength right where the building moves: wall-floor junctions, slab cracks and pipe penetrations.
A few practical notes from the video:
- Cut the membrane to size in short lengths rather than wrestling a long roll.
- Do the perimeter first, then move to the floor joints.
- Use a paintbrush instead of a roller if that’s easier. In tight corners and around the floor trap, a brush works the material in far better.
Once everything is covered, the first coat dries for 24 hours.
Step 6: Second coat, another 24 hours
“Now I’ve waited 24 hours, I’m going to apply my second coat.”
Then another 24 hours of drying, and only then is the tape removed and the job called done. Count it up. From primer to finished membrane, this is a three- to four-day process for one small floor. Anyone who promises to waterproof and tile your bathroom on the same day is skipping cure time somewhere.
What changes in an Indian bathroom
The DIY method is sound, but Indian bathrooms bring a few complications the video doesn’t cover:
- Sunken slabs. Many Aurangabad flats have a sunken bathroom slab filled with brick bats or debris. If water gets into that filling, it sits there for years and seeps into the flat below. The waterproofing has to be done on the structural slab before the filling, and again on top of the filling before tiling.
- Pipe penetrations and the floor trap. These are the leak points in most of the bathrooms we open up. Each one needs a sealed collar and reinforcing fabric around it.
- Material choice. Indian practice leans towards two-component polymer-modified cementitious coatings and acrylic or PU membranes, rather than ready-mixed tubs. We’ve decoded which product goes where in our guide to Dr Fixit waterproofing chemicals.
- Testing before tiling. The video ends at “job done”. We’d add one more step: a ponding test, where you flood the floor and check the ceiling below before a single tile goes down. It’s the cheapest insurance in the whole renovation.
For a full Indian-site walkthrough, including the chemical ratio and the khangar detail at the junctions, read Bathroom Waterproofing Done Right.
The real takeaway
The products in this video aren’t magic. What makes the method work is the discipline: a clean surface, primer taken up the walls, cracks treated first, fabric at every joint, two coats and a full day of curing between each stage. Skip any one of those and you’re paying for it later, usually when your downstairs neighbour knocks on your door.
How Vedh handles this in Aurangabad
At Vedh, bathroom waterproofing is the core of our bathroom work. We use a proprietary 7-layer system that builds on the same principles shown here: slab preparation, priming, crack and junction treatment, fabric reinforcement and multiple cured coats. We add the sunken-slab and pipe-penetration details that Indian bathrooms need, and we pond-test every floor before tiling. Every job runs on clear 40/40/20 payment terms and carries a 1-year free workmanship warranty. If your bathroom is leaking, or you’re planning a renovation and want it done right the first time, WhatsApp Santosh on +91 92727 31023 or fill the form at /contact.
FAQs
How many coats of waterproofing does a bathroom floor need? +
At least two coats, applied in opposite directions, with each coat fully dried before the next. Most liquid membranes need around 24 hours between coats. A single thick coat cures unevenly and tends to leave pinholes.
How high should bathroom waterproofing go up the wall? +
On the general floor area, take it at least 150–300 mm up the wall. Inside the shower zone, carry it much higher. The video's guideline is at least 1.8 metres. In Indian bathrooms with a wall-mounted shower, waterproofing the full wet wall up to shower-head height is a sensible minimum.
Do I need to break my tiles to fix bathroom leakage to the flat below? +
Usually yes, if the leak comes from failed waterproofing under the tiles. Grout sealers and surface coatings can slow a minor seepage, but a proper fix means taking the floor down to the slab, repairing it and re-waterproofing before you tile again.
What is the reinforcing membrane or fabric used in waterproofing? +
It is a thin polyester or fibreglass mesh laid into wet waterproofing at corners, joints and cracks. It lets the coating bridge small movements in the structure without splitting, which is exactly where most bathroom leaks start.